Hydropower Projects
In the field of investment, with the experience of an energy consultant, EVNPECC4 has researched, promoted project development and successfully executed the construction of 02 small and medium hydropower projects, bringing high efficiency and contributing to the preservation and development of corporate capital. In the current period, EVNPECC4 continues to research and invest in renewable energy and biomass fields.
1. SREPOK 4A HYDROPOWER PLANT - 64 MW
Investor: Buon Don Hydropower Joint Stock Company (BDHC)
Location: Dak Lak
Operation year: 2014
EVNPECC4's contributed capital at BDHC as of June 30, 2022: VND 103,850,000,000
EVNPECC4’s owning shares (%): 31%
Average annual power output: 250 million kWh
Srepok 4A Hydropower Plant, belonging to Buon Don Hydropower Joint Stock Company, has a designed capacity of 64 MW and started construction in 2010. In 2014, Srepok 4A Hydropower Plant officially generated commercial electricity. Annually, the plant will provide about 250 million kWh of clean electrical energy to the national grid.
Srepok Hydropower Plant 4A
2. SON GIANG HYDROPOWER PLANT - 10 MW
Investor: Son Giang Power Joint Stock Company (SGPC)
Location: Phu Yen
Operation year: 2019
EVNPECC4's contributed capital at SGPC as of June 30, 2022: VND 5,000,000,000
EVNPECC4’s owning shares (%): 6.46%
Average annual power output: 44.5 million kWh
Son Giang Hydropower Plant, belonging to Son Giang Power Joint Stock Company, has a designed capacity of 10 MW and started construction in 2016. In 2019, Son Giang Hydropower Plant officially generated commercial electricity. Annually, the plant will provide clean electrical energy of about 44.5 million kWh for the national grid.
Son Giang Hydropower Plant