NEWS & EVENTS

Can the completion of Phase 1 of the 220kV Bo Y Substation and interconnection lines be achieved on schedule?

04/11/2022 00:00:00

According to the Phase 1 objectives, the 220kV Bo Y Substation and the 220kV interconnection lines will be energized with 4 transformer bays in November 2022. How is the Power Project Management Board 2 (under Vietnam Electricity) overseeing the project? Can the Phase 1 objectives be achieved or not?

The 220kV Bo Y Substation and the 220kV interconnection lines, although a relatively small-scale project, hold significant importance in ensuring the import of electricity from the Nam Kong 1, 2, and 3 hydropower plants (Laos) into the Vietnamese power system following the commitments between the two countries' Party and Government.

The 220kV Bo Y Substation and interconnection lines t is currently under construction

Vietnam Electricity (EVN) has entrusted the Power Project Management Board 2 (EVNPMB 2) to oversee the project. Mr. Nguyen Khang - Deputy Head of the Safety Technical Department, Deputy Head of the Project Steering Committee under EVNPMB 2, has shown great interest and regularly pushed for progress.

Throughout the implementation process, the project has encountered several difficulties. Specifically, the site for the substation was only handed over on April 26, 2022. The 220kV interconnection lines were entirely handed over regarding foundation positions on October 21, 2022, as some sections pass through natural forests, leading to complex procedures.

Another challenge is that two-thirds of the substation area is on hills, while the remaining part is in a valley. Moreover, the height of the embankment reaches over 30 meters with an estimated volume of 65,000 m3, not to mention the associated reinforcement works.

Sharing more about the project's difficulties, Mr. Dang Ngoc Phuong - Deputy Project Supervision Consultant of the 220kV Bo Y Substation and interconnection lines project (under the Power Engineering Consulting Joint Stock Company 4 -EVNPECC4) stated that this year's weather conditions have been harsher, with frequent heavy rainfall, averaging 23-25 days/month. As a result, land leveling and earth filling have become challenging, and the duration has been prolonged compared to the original plan. Furthermore, the project has specific locations where power poles pass through natural forests, making it impossible to open access roads, necessitating manual construction processes.

Facing these obstacles, EVNPMB 2 and the contractors have proposed dividing the project into two phases. Phase 1 aims to energize 4 transformer bays by November 30, 2022, while Phase 2 seeks to complete the project by mid-January 2023.

Mr. Tran Trieu Son - Deputy Head of the Equipment Procurement Department, Deputy Head of the Project Steering Committee under EVNPMB 2, stated that to date, the construction units had completed over 60% of the equipment installation, with ongoing work on the remaining 3 foundation positions and 7 out of 17 wire stringing sections. The Project Management Board strives to complete the installation work, conduct testing of the substation in Phase 1, and complete the 220kV transmission line for commissioning by November 28, 2022.

The contractors are striving to complete the project successfully

According to Mr. Mai Duc Cuong - Commander-in-Chief of the Consortium of Contractors for Construction of the LILAMA-TOJI and Power Construction Installation Company Limited No.4 (PCC4), the initial implementation of the project did not meet the schedule, but it has now essentially caught up with the Phase 1 plan. "Throughout the implementation process, the contractors have received regular attention and support from the investor. The investor has promptly resolved any design and land-related obstacles for the contractors. We have full confidence in meeting the set schedule," emphasized Mr. Cuong.

The Project Steering Committee under EVNPMB 2 is closely monitoring the progress, urging the construction contractors to increase workforce and equipment deployment to three daily shifts. They are also coordinating closely with relevant agencies to complete the necessary legal procedures to ensure the commissioning of Phase 1 according to the set plan.

220kV Bo Y Substation and Interconnection Line:

  • Investor: Vietnam Electricity (EVN)
  • Project Management: Power Project Management Board 2
  • Engineering and Supervision Consulting Firm: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4)
  • Consortium of Construction Contractors: Vietnam Machinery Installation Corporation, PCC4, and TOJI Group Corporation
  • Total Investment: 181 billion VND
  • The project is located in Ngoc Hoi district, Kon Tum province.
  • Construction commenced in April 2022 and is expected to be completed by January 2023.

Project Scope:

  • Construction of a new 220kV Bo Y Substation, including 10 bays in total. In this phase, 6 bays will be installed.
  • Construction of a 6 km, 2-circuit 220kV transmission line connecting the Bo Y Substation to the 220kV Interconnection Line of Nam Kong 2 and 3 Substations (Laos).
  • Construction of a 0.8 km, 4-circuit 220kV transmission line connecting the Bo Y Substation to the 220kV Xekaman 1 (Laos) - Pleiku 2 transmission line

Source: EVN

 

Related article

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

At 20:22 on April 29th 2026, the National Power Transmission Corporation (EVNNPT), in coordination with the Power Transmission Project Management Board (NPTPMB) and the National Power System and Market Operation Co., Ltd. (NSMO), successfully energized the project to upgrade the capacity of the 500kV Hoa Binh Substation, increasing its capacity from 1,350MVA to 1,800MVA.

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Liberation Day (30th April) and International Labor Day (1st May) holidays as following

Announcement of Hung Kings’ Commemoration Day 2026

Announcement of Hung Kings’ Commemoration Day 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Hung Kings' Commemoration Day holiday as following:

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

On April 9th 2026, in Phu Tho, the Labor Union of the National Power Transmission Corporation (EVNNPT) visited and encouraged employees of the Power Transmission Project Management Board (NPTPMB), along with contractors working on the 500kV Hoa Binh Substation Capacity Upgrade Project—one of EVNNPT’s key and urgent power transmission projects.

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

On the morning of March 19th, the Vietnam Bank for Agriculture and Rural Development (Agribank), in coordination with Vietnam Environment Joint Stock Company (a member of the Amaccao Group), held a signing ceremony for a credit agreement and an insurance contract to implement the Khanh Son waste-to-energy plant project (Hoa Khanh Ward, Da Nang City).

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 2827215

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice