NEWS & EVENTS

Can the completion of Phase 1 of the 220kV Bo Y Substation and interconnection lines be achieved on schedule?

04/11/2022 00:00:00

According to the Phase 1 objectives, the 220kV Bo Y Substation and the 220kV interconnection lines will be energized with 4 transformer bays in November 2022. How is the Power Project Management Board 2 (under Vietnam Electricity) overseeing the project? Can the Phase 1 objectives be achieved or not?

The 220kV Bo Y Substation and the 220kV interconnection lines, although a relatively small-scale project, hold significant importance in ensuring the import of electricity from the Nam Kong 1, 2, and 3 hydropower plants (Laos) into the Vietnamese power system following the commitments between the two countries' Party and Government.

The 220kV Bo Y Substation and interconnection lines t is currently under construction

Vietnam Electricity (EVN) has entrusted the Power Project Management Board 2 (EVNPMB 2) to oversee the project. Mr. Nguyen Khang - Deputy Head of the Safety Technical Department, Deputy Head of the Project Steering Committee under EVNPMB 2, has shown great interest and regularly pushed for progress.

Throughout the implementation process, the project has encountered several difficulties. Specifically, the site for the substation was only handed over on April 26, 2022. The 220kV interconnection lines were entirely handed over regarding foundation positions on October 21, 2022, as some sections pass through natural forests, leading to complex procedures.

Another challenge is that two-thirds of the substation area is on hills, while the remaining part is in a valley. Moreover, the height of the embankment reaches over 30 meters with an estimated volume of 65,000 m3, not to mention the associated reinforcement works.

Sharing more about the project's difficulties, Mr. Dang Ngoc Phuong - Deputy Project Supervision Consultant of the 220kV Bo Y Substation and interconnection lines project (under the Power Engineering Consulting Joint Stock Company 4 -EVNPECC4) stated that this year's weather conditions have been harsher, with frequent heavy rainfall, averaging 23-25 days/month. As a result, land leveling and earth filling have become challenging, and the duration has been prolonged compared to the original plan. Furthermore, the project has specific locations where power poles pass through natural forests, making it impossible to open access roads, necessitating manual construction processes.

Facing these obstacles, EVNPMB 2 and the contractors have proposed dividing the project into two phases. Phase 1 aims to energize 4 transformer bays by November 30, 2022, while Phase 2 seeks to complete the project by mid-January 2023.

Mr. Tran Trieu Son - Deputy Head of the Equipment Procurement Department, Deputy Head of the Project Steering Committee under EVNPMB 2, stated that to date, the construction units had completed over 60% of the equipment installation, with ongoing work on the remaining 3 foundation positions and 7 out of 17 wire stringing sections. The Project Management Board strives to complete the installation work, conduct testing of the substation in Phase 1, and complete the 220kV transmission line for commissioning by November 28, 2022.

The contractors are striving to complete the project successfully

According to Mr. Mai Duc Cuong - Commander-in-Chief of the Consortium of Contractors for Construction of the LILAMA-TOJI and Power Construction Installation Company Limited No.4 (PCC4), the initial implementation of the project did not meet the schedule, but it has now essentially caught up with the Phase 1 plan. "Throughout the implementation process, the contractors have received regular attention and support from the investor. The investor has promptly resolved any design and land-related obstacles for the contractors. We have full confidence in meeting the set schedule," emphasized Mr. Cuong.

The Project Steering Committee under EVNPMB 2 is closely monitoring the progress, urging the construction contractors to increase workforce and equipment deployment to three daily shifts. They are also coordinating closely with relevant agencies to complete the necessary legal procedures to ensure the commissioning of Phase 1 according to the set plan.

220kV Bo Y Substation and Interconnection Line:

  • Investor: Vietnam Electricity (EVN)
  • Project Management: Power Project Management Board 2
  • Engineering and Supervision Consulting Firm: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4)
  • Consortium of Construction Contractors: Vietnam Machinery Installation Corporation, PCC4, and TOJI Group Corporation
  • Total Investment: 181 billion VND
  • The project is located in Ngoc Hoi district, Kon Tum province.
  • Construction commenced in April 2022 and is expected to be completed by January 2023.

Project Scope:

  • Construction of a new 220kV Bo Y Substation, including 10 bays in total. In this phase, 6 bays will be installed.
  • Construction of a 6 km, 2-circuit 220kV transmission line connecting the Bo Y Substation to the 220kV Interconnection Line of Nam Kong 2 and 3 Substations (Laos).
  • Construction of a 0.8 km, 4-circuit 220kV transmission line connecting the Bo Y Substation to the 220kV Xekaman 1 (Laos) - Pleiku 2 transmission line

Source: EVN

 

Related article

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

The Gia Lai Provincial People’s Committee has recently approved the investment policy and concurrently approved Vietnam Electricity (EVN) as the investor for the Se San 3 Hydropower Plant Expansion Project. The project will be implemented in Ia Ly Commune, Gia Lai Province, and Ya Ly Commune, Quang Ngai Province.

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

The Gia Lai Provincial People’s Committee issued Decision No. 3625/QD-UBND dated August 23, 2026, approving the investment policy and simultaneously approving Vietnam Electricity (EVN) as the investor of the Sesan 4 Hydropower Plant Expansion Project. The project has a design capacity of 120MW and a total investment of nearly VND 3 trillion.

Announcement of National Day Holiday on September 2nd 2026

Announcement of National Day Holiday on September 2nd 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the National Day holiday 2026

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

On August 24th 2026, at its Headquarters at 11 Hoang Hoa Tham Street, Nha Trang Ward, Khanh Hoa Province, Power Engineering Consulting Joint Stock Company 4 (PECC4), stock code TV4, successfully organized its 2026 Extraordinary General Meeting of Shareholders in accordance with the prescribed procedures, formalities, and applicable laws. The Meeting was attended and directed by representatives of Vietnam Electricity (EVN), including Ms. Pham Thi Thuy Ha - EVN’s Board Member; Mr. Tran Vinh Thai - Deputy Head of Corporate Planning Department; and Ms. Pham Huong Giang - Officer of Corporate Planning Department, together with 46 PECC4 shareholders, representing 14,850,719 shares, equivalent to 75.07% of the Company’s total voting shares.

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

On the afternoon of August 18th 2026, at My Anh Football Field in Nha Trang Ward, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in a football tournament commemorating the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026). The tournament was organized by the Cybersecurity and High-Tech Crime Prevention Division of Khanh Hoa Provincial Police.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3096948

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice