NEWS & EVENTS

Can the completion of Phase 1 of the 220kV Bo Y Substation and interconnection lines be achieved on schedule?

04/11/2022 00:00:00

According to the Phase 1 objectives, the 220kV Bo Y Substation and the 220kV interconnection lines will be energized with 4 transformer bays in November 2022. How is the Power Project Management Board 2 (under Vietnam Electricity) overseeing the project? Can the Phase 1 objectives be achieved or not?

The 220kV Bo Y Substation and the 220kV interconnection lines, although a relatively small-scale project, hold significant importance in ensuring the import of electricity from the Nam Kong 1, 2, and 3 hydropower plants (Laos) into the Vietnamese power system following the commitments between the two countries' Party and Government.

The 220kV Bo Y Substation and interconnection lines t is currently under construction

Vietnam Electricity (EVN) has entrusted the Power Project Management Board 2 (EVNPMB 2) to oversee the project. Mr. Nguyen Khang - Deputy Head of the Safety Technical Department, Deputy Head of the Project Steering Committee under EVNPMB 2, has shown great interest and regularly pushed for progress.

Throughout the implementation process, the project has encountered several difficulties. Specifically, the site for the substation was only handed over on April 26, 2022. The 220kV interconnection lines were entirely handed over regarding foundation positions on October 21, 2022, as some sections pass through natural forests, leading to complex procedures.

Another challenge is that two-thirds of the substation area is on hills, while the remaining part is in a valley. Moreover, the height of the embankment reaches over 30 meters with an estimated volume of 65,000 m3, not to mention the associated reinforcement works.

Sharing more about the project's difficulties, Mr. Dang Ngoc Phuong - Deputy Project Supervision Consultant of the 220kV Bo Y Substation and interconnection lines project (under the Power Engineering Consulting Joint Stock Company 4 -EVNPECC4) stated that this year's weather conditions have been harsher, with frequent heavy rainfall, averaging 23-25 days/month. As a result, land leveling and earth filling have become challenging, and the duration has been prolonged compared to the original plan. Furthermore, the project has specific locations where power poles pass through natural forests, making it impossible to open access roads, necessitating manual construction processes.

Facing these obstacles, EVNPMB 2 and the contractors have proposed dividing the project into two phases. Phase 1 aims to energize 4 transformer bays by November 30, 2022, while Phase 2 seeks to complete the project by mid-January 2023.

Mr. Tran Trieu Son - Deputy Head of the Equipment Procurement Department, Deputy Head of the Project Steering Committee under EVNPMB 2, stated that to date, the construction units had completed over 60% of the equipment installation, with ongoing work on the remaining 3 foundation positions and 7 out of 17 wire stringing sections. The Project Management Board strives to complete the installation work, conduct testing of the substation in Phase 1, and complete the 220kV transmission line for commissioning by November 28, 2022.

The contractors are striving to complete the project successfully

According to Mr. Mai Duc Cuong - Commander-in-Chief of the Consortium of Contractors for Construction of the LILAMA-TOJI and Power Construction Installation Company Limited No.4 (PCC4), the initial implementation of the project did not meet the schedule, but it has now essentially caught up with the Phase 1 plan. "Throughout the implementation process, the contractors have received regular attention and support from the investor. The investor has promptly resolved any design and land-related obstacles for the contractors. We have full confidence in meeting the set schedule," emphasized Mr. Cuong.

The Project Steering Committee under EVNPMB 2 is closely monitoring the progress, urging the construction contractors to increase workforce and equipment deployment to three daily shifts. They are also coordinating closely with relevant agencies to complete the necessary legal procedures to ensure the commissioning of Phase 1 according to the set plan.

220kV Bo Y Substation and Interconnection Line:

  • Investor: Vietnam Electricity (EVN)
  • Project Management: Power Project Management Board 2
  • Engineering and Supervision Consulting Firm: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4)
  • Consortium of Construction Contractors: Vietnam Machinery Installation Corporation, PCC4, and TOJI Group Corporation
  • Total Investment: 181 billion VND
  • The project is located in Ngoc Hoi district, Kon Tum province.
  • Construction commenced in April 2022 and is expected to be completed by January 2023.

Project Scope:

  • Construction of a new 220kV Bo Y Substation, including 10 bays in total. In this phase, 6 bays will be installed.
  • Construction of a 6 km, 2-circuit 220kV transmission line connecting the Bo Y Substation to the 220kV Interconnection Line of Nam Kong 2 and 3 Substations (Laos).
  • Construction of a 0.8 km, 4-circuit 220kV transmission line connecting the Bo Y Substation to the 220kV Xekaman 1 (Laos) - Pleiku 2 transmission line

Source: EVN

 

Related article

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

The commissioning of the 500kV – 900MVA AT1 transformer has increased the capacity of 500kV Di Linh Substation from 900MVA to 1,350 MVA, initially enhancing its capability to evacuate power generated by power sources in the region.

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

In celebration of the 96th anniversary of the Vietnam Women's Union (20/10/1930 – 20/10/2026) and the 16th anniversary of Vietnamese Women's Day (20/10/2010 – 20/10/2026), with the approval of the Company's Executive Board, the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4) organized a gathering for female employees at the Company's headquarters (11 Hoang Hoa Tham Street, Nha Trang), followed by a social gathering at I-Resort Nha Trang. The event took place in a warm and joyful atmosphere, bringing meaningful moments and memorable experiences to PECC4's female employees.

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

500kV Krong Buk - Tay Ninh 1 tranmission line project is invested by the National Power Transmission Corporation (EVNNPT) and managed by the Southern Power Projects Management Board (SPMB). The consortium comprising Power Engineering Consulting Joint Stock Company 4 (PECC4), Power Engineering Consulting Joint Stock Company 3 (PECC3), and Power Engineering Consulting Joint Stock Company 2 (PECC2) has signed Contract No.259//HĐTV-SPMB-PECC3-PECC2-PECC4 on 18/9/2026 with the Southern Power Projects Management Board (SPMB) for Package No. 5: Provision of construction survey consulting services; preparation of the technical design and construction cost estimate; detailed design; and bidding documents for the 500kV Krong Buk – Tay Ninh 1 Transmission Line Project.

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Caring for employees’ spiritual well-being and nurturing the younger generation, particularly the children of PECC4 employees, have always received great attention from the Executive Board and the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4). This annual tradition has been preserved and continuously promoted over the years, becoming a meaningful part of PECC4’s corporate culture and reflecting the Company’s strong humanitarian values.

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

On September 25th 2026, in Nam Nha Trang Ward, the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3 was successfully held. As the Head of the Cluster in 2026, Power Engineering Consulting Joint Stock Company 4 (PECC4) was honored to host the event.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3251505

Copyright © 2026 Power Engineering Consulting Joint Stock Company 4