NEWS & EVENTS

Commencement of 220kV Ninh Hoa (Van Ninh) Substation and Connecting Transmission Line project

03/01/2024 21:36:22

On December 29, 2023 in Khanh Hoa province, the National Power Transmission Project Management Board (NPTPMB) organized the groundbreaking ceremony for the 220kV Ninh Hoa (Van Ninh) Substation and Connecting Transmission Line project. According to schedule, the project is expected for completion in January 2025.

The project owner is National Power Transmission Corporation (EVNNPT). NPTPMB is the project management unit. Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) provides engineering and supervision services. Power Transmission Company 3 will operate the substation after completion.

Delegates performed the ceremony for project implementation

The project is located in Suoi Hang village, Van Khanh commune, Van Ninh district, Khanh Hoa province. The location was approved by Khanh Hoa Provincial People’s Committee in Document No. 88/UBND-KT dated January 6, 2020.

The project will install 01 220/110/22kV transformer with capacity of 250MVA. The 220kV side uses a double-busbar scheme with bus-tie, comprising 10 bays. In this phase, equipment for 06 bays (04 outgoing feeders, 01 incoming feeder and 01 circuit breaker bay) will be installed, configuring a double-busbar scheme. 01 bus-tie bay, 01 incoming feeder and 02 outgoing feeders are reserved for the next phase.

The 110kV side uses a double-busbar scheme with bus-tie, comprising 15 bays. In this phase, equipment for 06 bays (04 outgoing feeders, 01 incoming feeder and 01 circuit breaker bay) will be installed. 06 outgoing feeders, 01 incoming feeder of 250MVA transformer, 01 bus-tie bay and 01 condenser bay are reserved for the next phase.

The 22kV side uses a block diagram with outdoor equipment to self-supply power through substation’s transformers. Control, protection, metering, communication and SCADA system: Integrated control system using computers following EVN and EVNNPT’s regulations, protection and metering devices meeting prevailing standards.

Connecting transmission lines: Building new 220kV , 4 circuits, about 250m long transmission lines to connect with existing 220kV Tuy Hoa – Nha Trang transmission lines.

Participating units commit to meeting the project timeline

The project aims to meet the load demand and ensure safe operation of 110kV substations in Northern Khanh Hoa province and Southern Phu Yen province, especially providing electricity for Van Phong Economic Zone. It helps improve reliability of electricity supply for socio-economic development in Khanh Hoa province.

The project also ensures safe operation and avoids overloading risks for 110kV lines and voltage drops in the Northern Khanh Hoa province in case of failures on related 110kV lines.

In his speech, Mr. Nguyen Quang Anh, NPTPMB’s Deputy General Director said: This is an important project to ensure stable power supply for Khanh Hoa and neighboring provinces. Hence, NPTPMB requires all contractors to strictly follow technical standards and processes, effectively manage occupational safety, health and environmental matters, and ensure construction quality.

NPTPMB proposes contractors and supervision consultant to strengthen workforce to closely coordinate with the Project Executive Board and related parties in meeting EVNNPT’s requirements on quality and progress.

Perspective drawing of 220kV Ninh Hoa (Van Ninh) Substation and Connecting Transmission Line

Mr. Nguyen Huu Danh – Chairman of Van Khanh Commune People’s Committee highly appreciated NPTPMB’s close coordination with local authorities in recent time so that the whole political system from commune to district level promptly focused on site clearance. So far, most of project areas have been cleared and handed over to the Project Owner. Mr. Danh expected that NPTPMB would continue to pay attention to social welfare activities in the commune, environmental protection, and concentration of resources to ensure project schedule.

Representatives of the construction contractor committed to allocate suitable resources, ensure occupational safety, quality and progress in line with the investor’s set targets.

NPT.COM.VN

Related article

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

The Gia Lai Provincial People’s Committee has recently approved the investment policy and concurrently approved Vietnam Electricity (EVN) as the investor for the Se San 3 Hydropower Plant Expansion Project. The project will be implemented in Ia Ly Commune, Gia Lai Province, and Ya Ly Commune, Quang Ngai Province.

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

The Gia Lai Provincial People’s Committee issued Decision No. 3625/QD-UBND dated August 23, 2026, approving the investment policy and simultaneously approving Vietnam Electricity (EVN) as the investor of the Sesan 4 Hydropower Plant Expansion Project. The project has a design capacity of 120MW and a total investment of nearly VND 3 trillion.

Announcement of National Day Holiday on September 2nd 2026

Announcement of National Day Holiday on September 2nd 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the National Day holiday 2026

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

On August 24th 2026, at its Headquarters at 11 Hoang Hoa Tham Street, Nha Trang Ward, Khanh Hoa Province, Power Engineering Consulting Joint Stock Company 4 (PECC4), stock code TV4, successfully organized its 2026 Extraordinary General Meeting of Shareholders in accordance with the prescribed procedures, formalities, and applicable laws. The Meeting was attended and directed by representatives of Vietnam Electricity (EVN), including Ms. Pham Thi Thuy Ha - EVN’s Board Member; Mr. Tran Vinh Thai - Deputy Head of Corporate Planning Department; and Ms. Pham Huong Giang - Officer of Corporate Planning Department, together with 46 PECC4 shareholders, representing 14,850,719 shares, equivalent to 75.07% of the Company’s total voting shares.

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

On the afternoon of August 18th 2026, at My Anh Football Field in Nha Trang Ward, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in a football tournament commemorating the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026). The tournament was organized by the Cybersecurity and High-Tech Crime Prevention Division of Khanh Hoa Provincial Police.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3097071

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice