NEWS & EVENTS

Difficulties in the 220kV Dak Ooc Substation project and 220kV interconnection lines

24/02/2023 08:00:00

The 220kV Dak Ooc Substation project and the 220kV interconnection lines are targeted to be completed in the third quarter of 2023. However, at this point, the project still faces many challenges…

Challenges due to weather conditions:

The main scope of the project includes the construction of the 220kV Dak Ooc Switching Substation (in Nam Giang district, Quang Nam province) and the construction of approximately 13.4km of double-circuit 220kV transmission lines from the Nam Emoun Hydropower Plant (in Laos) to the 220kV Dak Ooc Switching Substation (in the territory of Vietnam). There is also a 2km section of four-circuit 220kV transmission lines from the 220kV Dak Ooc Switching Substation to the existing 220kV Xekaman 3 - Thanh My double-circuit transmission line.

The project is invested by Vietnam Electricity (EVN) as the owner, and Power Project Management Board 2 (PMB2) acts as the project management unit. Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) is responsible for surveying, engineering, and supporting the tender process and contract negotiation, as well as providing supervision consulting service.

On February 21, 2023, in Hanoi, Mr. Nguyen Tai Anh - Deputy General Director of EVN, chaired a meeting to review the progress with the units involved in the construction of the 220kV Dak Ooc Switching Substation and the 220kV interconnection lines.

According to PMB2, the 220kV Dak Ooc Switching Substation construction started in early September 2022. However, the weather has been unfavorable since then, with a recorded number of rainy days, 85 out of 122 days. Due to adverse weather conditions, the construction contractor could not proceed with the substation's foundation work. The contractor Lilama is continuing with land dredging to prepare for the substation's foundation work in early March 2023.

For the double-circuit 220kV interconnection lines, the construction contractor has poured concrete foundations at 3 out of 7 locations and is constructing at two other locations. The remaining 2 locations are still negotiating access routes with the local residents. As for the four-circuit 220kV interconnection lines, concrete foundations have been poured at 2 out of 8 locations, and construction is ongoing for one place. At the same time, access roads are being constructed for the remaining locations.

In addition to the biggest challenge of adverse weather conditions, the project also encounters difficulties and obstacles related to converting forest land use purposes for the foundation positions. The land clearance work has been delayed and faced many challenges due to some households disagreeing with the compensation plan that has been announced. Since many foundation positions pass through natural forests, materials and equipment are transported manually.

Which solution?

Mr. Nguyen Minh Tien, Deputy Director of Power Project Management Board 2 (PMB2), stated that in the face of these challenges, PMB2 had instructed the consortium of contractors to concentrate and strengthen the availability of equipment, workforce, overtime, and shifts to implement continuous construction to compensate for the shortage during the rainy season.

Rainy weather has greatly impacted the project's construction progress

Regarding the obstacles in the procedures for converting forest land use purposes, PMB2 will continue to closely follow the Ministry of Agriculture and Rural Development regarding submitting the conversion proposal for the Prime Minister's approval.

In terms of the land clearance work, PMB2 will coordinate with the functional agencies of Quang Nam province and Nam Giang district to resolve existing obstacles in land clearance. They will also work with the provincial People's Committee, relevant departments, and agencies to expedite the procedures for converting the land use purposes for the foundation positions immediately after obtaining the Prime Minister's approval.

Taking advantage of sunny weather, the construction units are carrying out their tasks

At the progress review meeting held on February 21st, Deputy General Director of Vietnam Electricity (EVN) Nguyen Tai Anh emphasized that the investment and construction of the project aim to fulfill the bilateral commitments on cooperation between the governments of Vietnam and Laos in the field of energy development, including importing electricity from the Nam Emoun Hydropower Plant (Laos) to Vietnam.

To complete the project in the third quarter of 2023, the Deputy General Director of EVN has instructed PMB2 to proactively work with local authorities, ministries, and departments to expedite the land use conversion process for land clearance and handover to the contractor. EVN also requires the leadership of PMB2 to be present at the construction site regularly to handle any arising situations.

For the contractor consortium, the Deputy General Director of EVN requests close collaboration and proactive execution of the work to jointly complete the project. This includes focusing on workforce and equipment and ensuring an adequate supply of materials and equipment. They must also find construction methods and measures to complete the foundation pillars in the natural forest area as soon as possible. Additionally, they should assign personnel at the construction site regularly to carry out author supervision tasks and promptly address design and technical requirements issues to meet the schedule and construction process.

EVN.COM.VN

Related article

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

The commissioning of the 500kV – 900MVA AT1 transformer has increased the capacity of 500kV Di Linh Substation from 900MVA to 1,350 MVA, initially enhancing its capability to evacuate power generated by power sources in the region.

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

In celebration of the 96th anniversary of the Vietnam Women's Union (20/10/1930 – 20/10/2026) and the 16th anniversary of Vietnamese Women's Day (20/10/2010 – 20/10/2026), with the approval of the Company's Executive Board, the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4) organized a gathering for female employees at the Company's headquarters (11 Hoang Hoa Tham Street, Nha Trang), followed by a social gathering at I-Resort Nha Trang. The event took place in a warm and joyful atmosphere, bringing meaningful moments and memorable experiences to PECC4's female employees.

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

500kV Krong Buk - Tay Ninh 1 tranmission line project is invested by the National Power Transmission Corporation (EVNNPT) and managed by the Southern Power Projects Management Board (SPMB). The consortium comprising Power Engineering Consulting Joint Stock Company 4 (PECC4), Power Engineering Consulting Joint Stock Company 3 (PECC3), and Power Engineering Consulting Joint Stock Company 2 (PECC2) has signed Contract No.259//HĐTV-SPMB-PECC3-PECC2-PECC4 on 18/9/2026 with the Southern Power Projects Management Board (SPMB) for Package No. 5: Provision of construction survey consulting services; preparation of the technical design and construction cost estimate; detailed design; and bidding documents for the 500kV Krong Buk – Tay Ninh 1 Transmission Line Project.

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Caring for employees’ spiritual well-being and nurturing the younger generation, particularly the children of PECC4 employees, have always received great attention from the Executive Board and the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4). This annual tradition has been preserved and continuously promoted over the years, becoming a meaningful part of PECC4’s corporate culture and reflecting the Company’s strong humanitarian values.

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

On September 25th 2026, in Nam Nha Trang Ward, the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3 was successfully held. As the Head of the Cluster in 2026, Power Engineering Consulting Joint Stock Company 4 (PECC4) was honored to host the event.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3251491

Copyright © 2026 Power Engineering Consulting Joint Stock Company 4