NEWS & EVENTS

Many electricity projects by EVN in Khanh Hoa require "clearance" for land acquisition

15/10/2020 00:00:00

On October 15th, in Khanh Hoa province, a working session took place between a delegation from Vietnam Electricity (EVN) and the provincial People's Committee to discuss solutions for resolving obstacles in compensation and land clearance (C&LC) for electricity projects in the province.

The Provincial People's Committee of Khanh Hoa included Mr. Nguyen Tan Tuan - Deputy Secretary of the Provincial Party Committee and Chairman of the Provincial People's Committee; Mr. Nguyen Duc Tai - Standing Deputy Chairman of the Provincial People's Committee; Mr. Le Huu Hoang - Deputy Chairman of the provincial People's Committee, as well as leaders of departments and sectors.

Representing EVN was Mr. Tran Dinh Nhan - EVN's General Director; Mr. Nguyen Tai Anh - EVN's Deputy General Director; Mr. Nguyen Tuan Tung - Chairman of the Board of Directors of the National Power Transmission Corporation (EVNNPT), Mr. Pham Le Phu - EVNNPT's General Director and Mr. Ngo Tan Cu - General Director of the Central Power Corporation.

Mr. Tran Dinh Nhan - General Director of EVN discussed the challenges in investing and constructing electricity projects in Khanh Hoa province

Regarding the projects invested by the National Power Transmission Corporation, there were issues with location agreements for substations and route directions for the 500kV Van Phong substation and 220kV interconnection lines. There were also obstacles in obtaining land price approvals and forest land use conversion permits for the 220kV Cam Ranh Substation and interconnection lines and the 220kV Nha Trang - Thap Cham Transmission Line (passing through Nha Trang City).

For projects invested by the Central Power Corporation, the Solar Power Plant project in Central Vietnam had yet to be approved for additional land use plans to proceed with C&LC-related activities. The upgrading project for the 110kV Nha Trang - Dien Khanh - Suoi Dau Transmission Line has not reached agreement on the route direction.

Several 110kV projects had yet to receive land price approvals (for establishing and approving compensation and payment plans for affected households). These projects included the capacity improvement project for the 110kV Suoi Dau - Cam Ranh Transmission Line, the 110kV interconnection line behind the 220kV Cam Ranh Substation, the 110kV Cam Ranh Airport Substation and interconnection lines, and the capacity improvement project for the 110kV Nha Trang - Ninh Hoa Transmission Line.

During the working session, EVN CEO Tran Dinh Nhan stated that the feasibility study report for the 500kV Van Phong Substation and 220kV interconnection lines had not been submitted to the authorized agency for review due to the lack of consensus from the Khanh Hoa Provincial People's Committee regarding the substation location and the route direction of the 220kV transmission line. This could lead to delays in the project's progress compared to the schedule stipulated in the Build-Operate-Transfer (BOT) contract for the Van Phong 1 Thermal Power Plant. This poses a risk for EVN regarding incurring compensation costs for Van Phong Power Company Limited.

EVN leadership also requested the province to approve the land price for the 220kV Nha Trang - Thap Cham Transmission Line project and the 220kV Cam Ranh Substation and interconnection to establish and support compensation and payment plans for affected residents.

Regarding projects by the Central Power Corporation, EVN proposed that Khanh Hoa province consider and approve specific land prices based on the land price proposals submitted by the Cam Ranh City People's Committee, district-level People's Committees, and the Department of Natural Resources and Environment.

During this working session, the Chairman of the provincial People's Committee of Khanh Hoa, Mr. Nguyen Tan Tuan, stated that the province had reached a consensus in principle regarding the location of the 500kV Van Phong Substation, which would be situated on a 6.6-hectare area within the land allocated for the Van Phong 1 Thermal Power Plant. EVNNPT (as the investor) and the Management Board of Central Power Projects were allowed to construct the 500kV Van Phong Substation after completing the procedures for land acquisition and leasing with the Van Phong Economic Zone Management Board and the relevant departments and agencies of Khanh Hoa province.

For other projects, the Chairman of the provincial People's Committee of Khanh Hoa requested that relevant departments and localities coordinate and guide EVN units to expedite the implementation of the projects to ensure national energy security. He also asked EVN units to proactively work with the provincial departments, sectors, and localities. They should promptly report to the province for resolution if there are any obstacles.

evn.com.vn

Related article

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

The Gia Lai Provincial People’s Committee has recently approved the investment policy and concurrently approved Vietnam Electricity (EVN) as the investor for the Se San 3 Hydropower Plant Expansion Project. The project will be implemented in Ia Ly Commune, Gia Lai Province, and Ya Ly Commune, Quang Ngai Province.

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

The Gia Lai Provincial People’s Committee issued Decision No. 3625/QD-UBND dated August 23, 2026, approving the investment policy and simultaneously approving Vietnam Electricity (EVN) as the investor of the Sesan 4 Hydropower Plant Expansion Project. The project has a design capacity of 120MW and a total investment of nearly VND 3 trillion.

Announcement of National Day Holiday on September 2nd 2026

Announcement of National Day Holiday on September 2nd 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the National Day holiday 2026

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

On August 24th 2026, at its Headquarters at 11 Hoang Hoa Tham Street, Nha Trang Ward, Khanh Hoa Province, Power Engineering Consulting Joint Stock Company 4 (PECC4), stock code TV4, successfully organized its 2026 Extraordinary General Meeting of Shareholders in accordance with the prescribed procedures, formalities, and applicable laws. The Meeting was attended and directed by representatives of Vietnam Electricity (EVN), including Ms. Pham Thi Thuy Ha - EVN’s Board Member; Mr. Tran Vinh Thai - Deputy Head of Corporate Planning Department; and Ms. Pham Huong Giang - Officer of Corporate Planning Department, together with 46 PECC4 shareholders, representing 14,850,719 shares, equivalent to 75.07% of the Company’s total voting shares.

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

On the afternoon of August 18th 2026, at My Anh Football Field in Nha Trang Ward, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in a football tournament commemorating the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026). The tournament was organized by the Cybersecurity and High-Tech Crime Prevention Division of Khanh Hoa Provincial Police.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3096933

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice