Electricity Industry News

29/08/2024

500kV circuit 3 transmission line from Quang Trach to Pho Noi: Success from entire political system strength

After more than 6 months of construction, the 500kV circuit 3 transmission line from Quang Trach to Pho Noi (including 4 sections) with a length of over 500km has been completed. This achievement is considered unprecedented compared to previous 500kV transmission line construction works.

Detail

20/08/2024

Energization of 500kV circuit-3 Nam Dinh 1 – Pho Noi transmission line

At 17:30, August 19th 2024, the National Power Transmission Corporation, the Northern Power Project Management Board (NPMB) coordinated with relevant units to successfully energize 2 circuits of 500kV circuir-3 transmission line, Nam Dinh 1 - Pho Noi section.

Detail

20/08/2024

Quynh Luu - Thanh Hoa 500kV Circuit-3 transmission line operational

The National Power Transmission Corporation (EVNNPT) and the Central Vietnam Power Project Management Board (CPMB) in collaboration with relevant units sent electricity to the Quynh Luu - Thanh Hoa 500kV Circuit-3 transmission line on August 19 morning.

Detail

19/08/2024

500kV circuit-3 transmission line, Nam Dinh I TPP – Pho Noi section is ready to be energized

The investor-level acceptance council of the 500kV circuit-3 transmission line project, Nam Dinh I TPP - Pho Noi section, had a meeting on the afternoon of August 16th 2024, in Hung Yen. Mr. Nguyen Ngoc Tan - Deputy General Director of the National Power Transmission Corporation (EVNNPT) and Mr. Bui Van Kien - Deputy General Director of EVNNPT, Chairman of the Acceptance Council affirmed that the project has met the conditions and is ready to be energized.

Detail

24/07/2024

GENERAL SECRETARY NGUYEN PHU TRONG: DEVOTED LEADER OF NATION AND PEOPLE

Respectfully presenting the article​​​​​​​: "GENERAL SECRETARY NGUYEN PHU TRONG: DEVOTED LEADER OF NATION AND PEOPLE" by General To Lam, Politburo Member and President of the Socialist Republic of Vietnam.

Detail

24/07/2024

PM calls for completion of 500kV Circuit-3 transmission line by National Day

Prime Minister Pham Minh Chinh has called for the completion of the 500kV Circuit-3 transmission line on the occasion of the 79th anniversary of August Revolution and National Day (September 2).

Detail

01/07/2024

Completed energization of 500kV circuit 3 transmission line, Thanh Hoa - Nam Dinh section

At 11:48 a.m., 30 June 2024, the National Power Transmission Corporation and the Northern Power Project Management Board (NPMB) in coordination with relevant units successfully energized the 500kV circuit 3 transmission line, Thanh Hoa - Nam Dinh section, meeting the Prime Minister's direction requirements.

Detail

28/06/2024

500kV circuit-3 transmission line project, Nam Dinh I TPP - Thanh Hoa section is ready for energization

The investor's Acceptance committee for the 500kV circuit-3 transmission line project, Nam Dinh I TPP - Thanh Hoa section had a meeting on the afternoon of June 27th 2024, in Thanh Hoa province. Mr. Luu Viet Tien - Deputy General Director of the National Power Transmission Corporation (EVNNPT), Chairman of the Acceptance committee, confirmed that the project has met all conditions and is ready for energization.

Detail

19/06/2024

Energizing the second component of the 500kV circuit 3 transmission line project

At 2:35 AM on June 18th 2024, at the 500kV Pho Noi substation, The Northern Vietnam Power Projects Management Board (NPMB) collaborated with related units to successfully energize the expansion of bays 585 and 586 at the 500kV Pho Noi substation and the transmission line section from the two expanded bays to position 319 of the 500kV circuit 3 transmission line project, Nam Dinh I TPP - Pho Noi section, two days ahead of the schedule required by EVNNPT.

Detail

10/06/2024

Prime Minister commended units for overcoming difficulties, striving to construct the 500 kV circuit 3 transmission line

On behalf of the Government, Prime Minister Pham Minh Chinh acknowledged, highly appreciated, and warmly commended the agencies, enterprises, workers, and the united spirit of the people with the highest determination to overcome all difficulties, mobilize all resources to focus on constructing the 500 kV circuit 3 transmission line from Quang Trach (Quang Binh) to Pho Noi (Hung Yen).

Detail

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 2827303

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice