Electricity Industry News

23/02/2024

EVN leaders worked with contractors, urged progress of the 500kV circuit-3 transmission line project

On the morning of February 21 in Hanoi, Mr. Dang Hoang An, Chairman of the Board of Vietnam Electricity (EVN), chaired a meeting with contractors participating in the 500kV circuit-3 transmission line project from Quang Trach to Pho Noi to review construction progress and urge contractors to mobilize human resources and equipment to speed up the project's progress. The meeting was held in a combination of in-person and online formats.

Detail

06/02/2024

Successful energization of 220kV Vinh Hao substation and connecting transmission line

At 02:05 a.m. on January 31st 2024, Power Project Management Board 2 (EVNPMB2), in coordination with related units, organized the energization to put the 220kV Vinh Hao Substation and 220kV connecting transmission line project into operation (in Vinh Hai village, Vinh Hao commune, Tuy Phong district, Binh Thuan province).

Detail

18/01/2024

Simultaneous construction of projects along the 500kV transmission line circuit 3 from Quang Trach to Pho Noi

On January 18, in Ha Tinh, Nghe An, Thanh Hoa and Thai Binh provinces, Vietnam Electricity (EVN) and the National Power Transmission Corporation (EVNNPT) organized the simultaneous groundbreaking ceremonies for construction of sections along the 500kV transmission line circuit 3 from Quang Trach (Quang Binh) to Pho Noi (Hung Yen).

Detail

04/01/2024

EVNNPT’s General Director Mr. Pham Le Phu encouraged contractors to work over Tet Holiday on 500kV Transmission Line, Circuit 3 Project

On January 1st 2024, General Director of National Power Transmission Corporation (EVNNPT) - Mr. Pham Le Phu and a working delegation from EVNNPT inspected the construction site and encouraged all contractor units constructing the 500kV Nam Dinh I Thermal Power Plant – Thanh Hoa Transmission Line, Circuit 3 project.

Detail

03/01/2024

Commencement of 220kV Ninh Hoa (Van Ninh) Substation and Connecting Transmission Line project

On December 29, 2023 in Khanh Hoa province, the National Power Transmission Project Management Board (NPTPMB) organized the groundbreaking ceremony for the 220kV Ninh Hoa (Van Ninh) Substation and Connecting Transmission Line project. According to schedule, the project is expected for completion in January 2025.

Detail

02/01/2024

The energization of 110kV Suoi Ngo Substation and Connecting Transmission Lines in Tay Ninh province

The 110kV Suoi Ngo Substation and Connecting Transmission Lines project in Tay Ninh province is invested by Southern Power Corporation (EVNSPC), managed by Southern Power Project Management Board – a subordinate unit of EVNSPC, and Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) is the consulting unit for survey and design from feasibility study stage to detailed design stage.

Detail

15/11/2023

220kV Phuoc Thai substation expansion project was officially energized and operated

The 220kV Phuoc Thai Substation Expansion Project is implemented at the existing 220kV Phuoc Thai Substation by expanding the existing substation area within the land area already allocated for the Phuoc Thai 1 Solar Power Plant project in Hoai Trung village, Phuoc Thai commune, Ninh Phuoc district, Ninh Thuan province.

Detail

14/11/2023

Construction Commencement of 500kV Binh Duong 1 Substation Project

On November 13, 2023, in Binh Duong, the National Power Transmission Corporation (EVNNPT), the Central Power Projects Management Board (CPMB), in coordination with related entities, organized the construction commencement of 500kV Binh Duong 1 Substation Project.

Detail

03/11/2023

Urgently construct Nam Dinh I TPP-Thanh Hoa 500kV transmission line

The National Power Transmission Corporation (EVNNPT) has just organized the construction of Nam Dinh I Thermal Power Plant (TPP)-Thanh Hoa 500kV transmission line, under the 500kV circuit 3 transmission line projects from Quang Trach ( Quang Binh) to Pho Noi (Hung Yen).

Detail

18/10/2023

Co-financiers of Bac Ai Pumped Storage Hydropower Plant Project conduct project appraisal

On October 16, in Hanoi, Mr. Nguyen Xuan Nam - EVN Deputy General Director worked with the co-financiers delegation of the Bac Ai Pumped Storage Hydropower Plant Project. This was the first working session in the sponsor group’s project appraisal program.

Detail

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3251479

Copyright © 2026 Power Engineering Consulting Joint Stock Company 4